Southampton General Hospital -
Oncology Ward
.png?width=750&height=500&name=Untitled%20design%20(46).png)
LST has successfully completed the construction of a new £7.3m cancer care unit in just six months.
The facility accommodates 27 inpatients and includes 11 single-bedside rooms. Spanning 1,800 sq m, the two-storey extension has been built atop an existing single-storey building, which houses another oncology department serving more than 150 people daily. The new structure has also been future-proofed to accommodate two additional floors at a later date.
A delayed start, primarily due to the Covid-19 pandemic, led to an exceptionally tight construction programme. The timing was critical, as the hospital needed patients to move from another ward into the new facility by 14 December 2020, to increase bed capacity in time for Christmas.
To accelerate the project and minimise any pandemic-related delays, the steel frame had been procured ahead of the main build. Moreover, building materials were ordered well in advance and in line with the work sequence, enabling storage at our head office ready for delivery to the site as needed.
The contract included two staircase structures, one designed to accommodate a patient evacuation lift. Once the main building works commenced, extensive surveys uncovered numerous services along the foundations' route. Consequently, we collaborated closely with structural engineers and designers to relocate the stairways, ensuring critical services remained uninterrupted.
This project posed significant logistical challenges. Our working area was completely encircled by a traffic route, impacting the design and management of our site compound. A main road south of the hospital was diverted around the compound in a new one-way system. After installing the steelwork, we expanded our working area to facilitate the delivery of additional materials and establish a new traffic route for installing the footings for the two staircases.
Extensive surveys ensured that occupiers were not disturbed by noise or vibrations. Very flexible working hours, including out-of-hours shifts, were necessary to meet the project's tight deadlines and minimise disruption.
Despite these challenges, all hurdles were overcome, and the new cancer care ward was handed over on schedule, opening to patients on 13 December 2020, a day earlier than anticipated.
-1.png?width=1080&height=1350&name=Untitled%20design%20(15)-1.png)
University Hospital Southampton - Oncology Ward
Download.png?width=750&height=500&name=Untitled%20design%20(32).png)
“Utmost thanks to the team for the phenomenal hard work, getting things organised and set up so efficiently against such incredibly tight timelines and opening a day ahead of the original target date.” “Thank you to LST Projects for their efficiency and adaptability in accommodating modifications along the way. From a clinical perspective we are very grateful to have brand new facilities for patient care.”
Dr Matthew Jenner, Consultant Haematologist, Haematology Clinical Lead at University Hospital Southampton.